Waiting for Construction Permits and Completing the Lot Ready Requirements Tomorrow will officially be 10 weeks from submitting the applications for construction permits for our Oregon new home build. The original time line said 6 weeks. There were a couple of supplemental items that needed to be addressed; they were submitted two weeks ago. We

group meeting discussing construction drawings, blue construction hat and plan on wood table.

Setting the Start Date for New Home Build

Reserve Date Meeting Overview Yesterday, we had our Reserve Date Meeting with the pre-construction administrator. We had been working with the sales consultant up until this point, but from here on out we will now be working with the pre-construction administrator. The purpose of this meeting was to set a start day for building and